2019 Diamond Award Recipient
Ocean Beach Ferry Terminal Reconstruction
The Ocean Beach Ferry Terminal on Fire Island, NY, was entirely reconstructed after Superstorm Sandy caused catastrophic flooding and debris damage in 2012. The Village of Ocean Beach, a ferry-access-only community and popular tourist destination, relies heavily on this terminal for economic and logistical connectivity. As the primary gateway for approximately 500,000 visitors each summer, the terminal’s role is crucial for sustaining local businesses and providing essential services to residents. FEMA and state project officers deemed the original terminal a complete loss, leading to a plan for a resilient, multi-use facility that serves as a first impression for tourists and a year-round asset for locals.
The new terminal’s design prioritized resilience, with a structure capable of withstanding severe weather conditions and flooding. The design incorporated treated wood, flood-resistant materials like closed-cell rigid insulation, and pressure-treated wood framing, ensuring the building can withstand periodic inundation without significant interior damage. Walls and floors below the flood elevation are equipped with materials that allow for quick drying and easy cleanup, reducing long-term maintenance costs and ensuring the terminal remains operational even after minor flooding events. Large, impact-resistant windows provide protection from high winds and debris while maximizing natural light, creating a bright and welcoming environment.
Energy efficiency was another key consideration, achieved through a combination of advanced building technologies. The terminal is equipped with a Variable Refrigerant Flow (VRF) system and an Energy Recovery Ventilator (ERV), which improve indoor air quality and reduce heating and cooling costs by capturing and reusing energy from the building’s air. The new design includes a relocated police department headquarters, positioning local law enforcement strategically within the heart of this community gateway. With its sustainable design and upgraded amenities, the terminal enhances the resilience and functionality of Ocean Beach’s transportation infrastructure while preserving its essential role in the community.
- Flood proofing allows water to enter and recede causing minimal damage to the building.
- Structurally, a continuous load path provides stability against hurricane force winds. Coastal impact resistant windows were also used.
- Includes energy saving variable refrigerant flow (VRF) systems with the capacity to operate simultaneously in heating and cooling.
- Phase 1 included installing 100+ timber piles for new foundation while avoiding existing bulkhead deadman system.
- Finished floor height of ferry terminal could not be elevated above the FEMA flood plain due to site limitations and tidal fluctuations for off-loading passengers.